The sixth of ten concrete pours for the lowest garage level of the future Montgomery County government office building has been completed at Lot 13 in Wheaton. County officials report that the first pour for the garage wall was completed last Thursday. The first garage ramp pour is scheduled for August 7, and 33 such pours will be necessary for the ramp to reach street level.
Underground Pepco work along Ennalls Avenue is anticipated to be completed next week. Verizon will begin its underground work within the next 14 days along Grandview Avenue. Ultimately, all overhead utility wires along the east side of Grandview will be undergrounded as part of this project.
County officials say the project remains on-schedule for a Summer 2020 delivery.