Tuesday, April 30, 2019

Wheaton Lot 13 project update

Excavation for the future town square at Montgomery County's Lot 13 project in the Wheaton Triangle is now complete, County officials say. In a somewhat-jarring development, however, the County is suddenly describing what has previously been called the Town Square as the "Town Plaza." With rough grading and haul-away of dirt now complete, a storm drain system for the square is now being installed; it will extend from Veirs Mill Road to Reedie Drive on either end.

The County office building at the center of the project is now 11 stories above Lot 13. Sprinkler systems are being installed on some garage levels now, and plumbing is going in on Floors 1-4. Above is an aerial view from a camera across the street released by Montgomery County.

No comments:

Post a Comment