Wednesday, July 24, 2019

Wheaton Lot 13 redevelopment project update (Photos)

Construction of the concrete building frame for the future Montgomery County Government office building at Lot 13 in the Wheaton Triangle is now complete, County officials say. Tyvek is installed on most floors, as construction of exterior walls continues. Interior wall framing is underway on floors 4 through 8, and utility installations are being performed as high as the 11th floor.
Nighttime sewer utility work should be completed by the end of this week, County officials report. Micro piles have been driven at the future Town Plaza site between the building and the Wheaton Metro station. Concrete foundations are currently being constructed at the plaza for elevated walkways, bio-retention areas, and the performance stage. Delivery is scheduled for Summer 2020.