Wheaton government office building nearing street level

The new Montgomery County government office building under construction at Public Parking Lot 13 in the Wheaton Triangle is nearing street level. County officials report that Verizon utility work related to the project continues along Grandview Avenue and Reedie Drive. However, Verizon's Triangle Lane work has been pushed back to early December.

New lateral water line connections to buildings along Ennalls Avenue will be hooked up by the WSSC this week. The agency will coordinate the hook-ups with each affected business. The new water line will be connected to an existing water main along Veirs Mill Road this week, as well.